Onsite pile treatment for real estate developer

Client : Real estate developer
Mandate: on site pile treatment to reuse soils for landscaping.

Initial concentration : B-C, C and RESC, mixed contamination
Final concentration :  A-B

Volume of soil treated : approx. 200,000 tons
Budget : 1,120,000$
Timeline : Less than 6 months, as planned

Difficulties encountered and solutions applied: The presence of residual materials since the operations took place on a ground where the woodland needed to be kept intact and where the presence of threatened species made every step more complicated.